On July 2, 2026, SBM signed a contract for the design and execution of works on railway line No. 309, on the section from km 14.250 to km 39.675 and at the Polanica-Zdrój station, covering signalling and control (LST), telecommunications, and non-traction power supply.
This is another task on the very same line where we are already intensively executing track works. Therefore, we would like to share the current progress of the works conducted under the project: “Works on railway line No. 309 Kłodzko Nowe – Kudowa-Zdrój – Track overhaul from km 14.250 to km 22.496 along with accompanying works.”
✅ We have completed the dismantling of the mainline track along the entire section covered by the investment.
✅ At the Szczytna station, we achieved 100% removal of tracks No. 1, 2, and 3, as well as 3 turnouts.
✅ At the Duszniki-Zdrój station, we completed the dismantling of track No. 5 and turnout No. 5.
✅ In total, we dismantled approximately 4 km of track panels.
In parallel, advanced earthworks and subgrade works are underway:
🔹 Ballast excavation has been fully completed on the section km 14+250 – 15+576 and on track No. 3 at the Szczytna station.
🔹 On the section km 16+232 – 21+638, these works have already reached 93% progress, and on tracks No. 1 and 2 (Szczytna station) – 50%.
🔹 Regarding drainage: we have completed 100% of open ditches and 20% of reinforced open ditches.
🔹 We are carrying out chemical soil stabilization and subgrade reinforcement.
🔹 Over 1,340 meters of subgrade boxing out (excavation) have already been completed.
🔧 We have also commenced the next stage of works:
• Replacement of turnout No. 2 in Szczytna,
• Replacement of turnout No. 1 in Duszniki-Zdrój,
• Track superstructure works on station tracks in Duszniki-Zdrój and Kulin Kłodzki.
We are delighted to expand our commitment on line No. 309, both in track works and within the newly acquired areas of LST, telecommunications, and power engineering. This is another step toward restoring full functionality and raising the standard of rail infrastructure in the Kłodzko Valley region.
SBM #Line309 #Railway #RailwayInfrastructure #RailwayConstruction #Modernization #LST #Telecommunications #PowerEngineering #Klodzko #KudowaZdroj #PolanicaZdroj #LowerSilesia #PKPPLK